Sistem Perawatan Alat Overhead Crane Dengan Metode Reliability Centered Maintenance (RCM) II dan Age Replacement

Authors

  • Ferdiansyah Wendyantoro Universitas Muhammadiyah Sidoarjo
  • Indah Apriliana Sari Wulandari Universitas Muhammadiyah Sidoarjo

DOI:

https://doi.org/10.47134/pslse.v3i2.695

Keywords:

Reliability Centered Maintenance (RCM) II, Age Replacement, Downtime, Efficiency

Abstract

Equipment maintenance is very important to ensure that the equipment operates properly within a certain period of time. PT. XYZ, which is engaged in the shipping industry, uses a demag type overhead crane with a capacity of 5 tons in its production process. This study aims to evaluate the reliability level of overhead cranes in existing conditions by calculating the reliability value. In addition, this study also aims to determine the critical component replacement interval appropriately so that replacement is carried out before downtime occurs. The results of the study identified three critical components, namely Contactor, Photoelectric Sensor, and Motor Hoist, with MTTR values ​​of 3.65667 hours, 4.15333 hours, and 1.1546 hours, respectively. The application of the age replacement method showed an increase in reliability: Contactor 39%, Photoelectric Sensor 40%, and Motor Hoist 83%. The recommended component replacement interval is every 11 days to reduce downtime and increase operational efficiency.

References

A. A. Muzakki, “Analisis Preventive Maintenance Mesin AM Korin Dengan Age Replacement di PT Nugraha Indah Citarasa Indonesia,” Jurnal Muara Sains, Teknologi, Kedokteran dan Ilmu Kesehatan, vol. 5, no. 2, p. 325, 2021. https://doi.org/10.24912/jmstkik.v5i2.9078

A. B. Sulistyo, & S. H. Mutiawati, “Usulan Jadwal Preventive Maintenance Komponen Ban pada Truk Tronton 20.000 KL Menggunakan Metode Age Replacement,” Jurnal INTECH Teknik Industri Universitas Serang Raya, vol. 7, no. 2, pp. 137–146, 2021. https://doi.org/10.30656/intech.v7i2.3891

A. B. Sulistyo, & S. Muhlis, “Optimasi Perawatan Mesin Overhead Crane pada PT. KNSS Dengan Metode Reliability Centered Maintenance (RCM) dan Failure Mode and Effect Analysis (FMEA),” Jurnal InTent (Jurnal Industri dan Teknologi Terpadu), vol. 5, no. 2, pp. 27–35, 2022. https://www.ejournal.lppm-unbaja.ac.id/index.php/intent/article/view/2447

A. B. Zamani, M. Nuruddin, & S. S. Dahda, “Penentuan Interval Penggantian Komponen Mesin Pengayakan Batu Bara Menggunakan Metode Age Replacement,” Jurnal Serambi Engineering, vol. VIII, no. 1, pp. 4341–4352, 2023.

A. Muhazir, Z. Sinaga, & R. D. Septiadi, “Perencanaan Perawatan Mesin Building Dengan Metode Reliability Centered Maintenance (RCM),” Jurnal Optimasi, vol. 10, no. 1, p. 120, 2024. https://doi.org/10.35308/jopt.v10i01.9263

A. Sastriawan, “Penjadwalan Pemeliharaan Mesin Produksi Menggunakan Reliability Centered Maintenance,” Jurnal Teknologi, vol. 14, no. 1, pp. 26–35, 2024. https://doi.org/10.35134/jitekin.v14i1.113

An Introduction to Reliability and Maintenance Engineering. New York: Times Roma, 1997.

D. Nurdiansyah, & A. H. D. P., “Analysis of Maintenance Management at PT. XYZ Power Plant (With MTTR, MTTF, and Availability Factors) and Development of Performance Improvement Program,” vol. 3, no. 9, pp. 3363–3376, 2024.

D. Wibisono, “Analisis Overall Equipment Effectiveness (OEE) Dalam Meminimalisasi Six Big Losses Pada Mesin Bubut (Studi Kasus di Pabrik Parts PT XYZ),” Jurnal Optimasi Teknik Industri, vol. 3, no. 1, pp. 7–13, 2021. https://doi.org/10.30998/joti.v3i1.6130

E. A. Agustiawan, M. Z. Fathoni, & D. Widyaningrum, “Usulan Preventive Maintenance Pada Mesin Hanger Shot Blast Kazo Dengan Menggunakan Metode Age Replacement di PT Barata Indonesia,” Matrik, vol. 22, no. 1, p. 73, 2021. https://doi.org/10.30587/matrik.v22i1.2715

I. L. Kusminah, A. N. Rachmat, & D. A. Nurjanah, “Optimizing Small Excavator Maintenance Activity Planning Using the Reliability-Centered Maintenance (RCM) Method II,” International Journal of Marine Engineering Innovation and Research, vol. 9, no. 1, pp. 208–217, 2024. https://doi.org/10.12962/j25481479.v9i1.19844

I. Ramadhan, & W. Widiasih, “Analisis Penggantian dan Perawatan pada Papermachine Bagian Wire dan Dryer Menggunakan Metode Reliability Centered Maintenance dan Age Replacement Pada PT. X,” Jurnal Tekstil: Jurnal Keilmuan dan Aplikasi Bidang Tekstil dan Manajemen Industri, vol. 6, no. 1, pp. 1–14, 2023. https://doi.org/10.59432/jute.v6i1.60

J. T. Juwandono, & J. Purnama, “Analisa Pemeliharaan Mesin Produksi dengan Metode Reliability Centered Maintenance (RCM) dan Age Replacement,” Jurnal Teknik Industri Terintegrasi, vol. 6, no. 3, pp. 483–492, 2023. https://doi.org/10.31004/jutin.v6i3.15768

K. Nisak, E. Nursanti, & T. Priyasmanu, “Analisis Tingkat Keandalan dan Penentuan Interval Waktu Pemeliharaan Mesin Pompa Air di Perumda Air Minum Tugu Tirta Kota Malang,” Jurnal Valtech, vol. 5, no. 2, pp. 217–223, 2022. https://ejournal.itn.ac.id/index.php/valtech/article/view/5644

Kevin Gilbert Wohon, Arini Anestesia Purba, & Budiani Fitria Endrawati, “Penjadwalan Perawatan Sparepart Mesin dengan Pendekatan Reliability Centered Maintenance dan Failure Mode Effect Analysis di PT ABC,” Jurnal Teknik Industri, vol. 13, no. 3, pp. 183–188, 2023. https://doi.org/10.25105/jti.v13i3.19139

M. Fahrurroji et al., “Usulan Perencanaan Perawatan Dengan Menggunakan Metode Reliability Centred Maintenance (RCM) di PT. Djabesmen,” Jurnal Industrial Xplore, vol. 6, no. 2, pp. 75–84, 2021.

N. M. Hidayatulloh, & T. Sukmono, “Determination of Production Instrumentation Equipment Maintenance Intervals in the Paper Industry,” PROZIMA (Productivity, Optimization and Manufacturing System Engineering), vol. 4, no. 1, pp. 23–31, 2021. https://doi.org/10.21070/prozima.v4i1.1275

R. M. Simanungkalit, S. Suliawati, & T. Hernawati, “Analisis Penerapan Sistem Perawatan dengan Menggunakan Metode Reliability Centered Maintenance (RCM) pada Cement Mill Type Tube Mill di PT Cemindo Gemilang Medan,” Blend Sains: Jurnal Teknik, vol. 2, no. 1, pp. 72–83, 2023. https://doi.org/10.56211/blendsains.v2i1.199

S. Sunaryo, J. Japri, Y. Yuhelson, & L. Hakim, “Implementasi RCM pada Mesin Diesel Deutz 20 kVA,” Turbo: Jurnal Program Studi Teknik Mesin, vol. 10, no. 1, pp. 42–52, 2021. https://doi.org/10.24127/trb.v10i1.1451

Downloads

Published

2026-06-27

How to Cite

Wendyantoro, F., & Indah Apriliana Sari Wulandari. (2026). Sistem Perawatan Alat Overhead Crane Dengan Metode Reliability Centered Maintenance (RCM) II dan Age Replacement. Physical Sciences, Life Science and Engineering, 3(2), 1–18. https://doi.org/10.47134/pslse.v3i2.695